FIN0373

Credit Committee request

Task

Credit Committee request

You are the senior project-finance credit officer for Halcyon Bank, N.A., which acts as Common Security Trustee and is a secured lender to Port Meridian Liquefaction, LLC (PML). At 10:00 UTC on 18 February 2019, PML asked the trustee to release $300.0 million from the Distribution Account to Port Meridian Holdings LLC on 22 February 2019.

Prepare the Distribution Decision Sheet for the Halcyon Credit Committee and the trustee operations team by 16:00 UTC on 20 February 2019. It must give a decision-ready contractual conclusion and a separate lender-credit position, supported by a corrected, auditable calculation of the applicable coverage tests and the forward cash plan. State the amount that can be released under the financing documents, the amount and structure Halcyon should support, and the exact instruction or conditions operations should use. Reconcile your result to the borrower’s submitted model, identify any reliance limits that affect execution, and quantify the sponsor timing consequence of any staged or deferred amount.

Use only the records below and information available by 18 February 2019. No external research is permitted. All amounts are in USD millions unless stated otherwise; monthly figures are cash amounts and may be used without tax or FX adjustments.

Transaction and status record

  • PML is a Delaware limited liability company that owns and operates three LNG liquefaction trains in Louisiana. Port Meridian Holdings LLC owns 100% of PML.
  • All senior facilities and notes are senior secured and pari passu in the common collateral. PML has no operating subsidiary and all project receipts pass through the controlled accounts described below.
  • The requested payment is an ordinary Restricted Payment. It is not a tax distribution, shareholder-loan repayment, Sponsor Case payment, Additional Equity Distribution, or project expenditure.
  • PML’s fiscal-quarter ends and Quarterly Payment Dates are 31 January, 30 April, 31 July, and 31 October.
  • All three train In-Service certificates and the Project Completion certificate became effective on 30 November 2018. The first scheduled principal installment under the senior facilities was paid in full on 31 January 2019.
  • No Restricted Payment has been made in February 2019. The requested transfer date is 22 February 2019.
  • No force-majeure election, termination trigger, payment default, Control Notice, waiver, or reservation-of-rights notice is outstanding. The four-quarter Distribution Account failure counter was zero at Project Completion; 31 January 2019 is the first date that can enter that count.
  • New York business days exclude Saturdays, Sundays, and New York bank holidays. For the relevant windows, 18 February and 27 May 2019 are holidays.
  • Counsel delivered a conformed closing set on 14 February 2019 and confirmed that the provisions reproduced below are operative as of the cut-off. The 17 September 2018 amendment did not change them. There are no other amendments or side letters affecting this request.

Executed financing-document extracts

Common Indenture dated 1 February 2013 and 2037 Notes Indenture dated 24 February 2017

The two indentures impose the same cumulative conditions for this payment. On the Restricted Payment Date:

  1. no Default or Event of Default may be continuing or result from the payment;
  2. the Project In-Service condition must have occurred;
  3. as of the applicable Calculation Date, both the Historical DSCR for the Calculation Period and the Projected DSCR for the following 12 months must be at least 1.25x;
  4. every required debt-service reserve must be funded; and
  5. an Authorized Officer must deliver a good-faith certificate with detailed calculations and reasonable assumptions.

Payments remain subject to the Accounts Agreement and may be made no more than once in a calendar month. For a 22 February 2019 payment, the Calculation Date is 31 January 2019, the Calculation Period is 1 February 2018 through 31 January 2019, and the projected period is 1 February 2019 through 31 January 2020.

For these indentures:

  • Cash Flow includes project operating cash received in the Revenue Account, interest transferred from non-reserve accounts, business-interruption insurance cash received, and owner equity or permitted subordinated-owner-loan cash received. It excludes debt proceeds, casualty or condemnation proceeds, asset-sale proceeds, and cash deposited in the Additional Proceeds Account.
  • CFADS is Cash Flow less cash O&M, secured-party fees and charges, and cash interest on Working Capital Debt.
  • Debt Service includes scheduled senior-debt fees, interest, and principal, but excludes Working Capital Debt, LC costs, voluntary or mandatory prepayments, principal payable only at final maturity, and hedge-termination amounts.
  • For Projected DSCR, cash may be included only if it arises under an agreement executed and effective by the Calculation Date, from non-reserve account interest, or from a business-interruption claim accepted in writing by the insurer by that date. The pass-through gas and transportation component is excluded together with the matching gas and transportation cash cost.

Second Amended and Restated Common Terms Agreement dated 30 June 2015

The Common Terms Agreement uses the same CFADS and Debt Service deductions, except that owner equity and subordinated-owner-loan cash is included in Cash Flow only when calculating the 1.15x maintenance covenant. It is not included in the Historical DSCR or Projected DSCR used for a Distribution Account release.

The maintenance covenant requires DSCR of at least 1.15x at each fiscal-quarter end. If the ratio is below 1.15x but above 1.00x, an owner may contribute cash within 10 business days after delivery of the calculation to raise it to 1.15x. The cure may be used no more than twice consecutively and four times over the life of an instrument.

The 30 April 2018 maintenance calculation was 1.09x before cure. It was delivered on 2 May 2018; the sponsor contributed $13.2 million on 7 May 2018, raising the accepted result to 1.15x. This was the first cure under every secured instrument and no cure was used in the preceding or following quarter. The agent’s default log dated 18 February 2019 records no continuing Default or CTA Event of Default.

Amended and Restated Accounts Agreement dated 30 June 2015

After Project Completion, residual Revenue Account cash is transferred to the Distribution Account only after the required operating funding, secured-party amounts, Debt Payment Account funding, reserve top-ups, permitted debt payments, and tax distributions have been made.

An ordinary Restricted Payment may be withdrawn from the Distribution Account only if:

  • no mandatory prepayment is then required;
  • no Default or CTA Event of Default is continuing, reasonably expected, or caused by the payment;
  • Historical DSCR and Projected DSCR are each at least 1.25x;
  • all required DSRAs are fully funded with eligible cash or reserve letters of credit;
  • Project Completion and the first facility principal installment have occurred;
  • payment is made no later than 25 business days after the latest fiscal-quarter end and before the last Quarterly Payment Date preceding final maturity; and
  • the trustee receives the executed Withdrawal/Transfer Certificate and detailed calculations. The Projected DSCR calculation must be reasonably acceptable to the trustee.

For this Accounts Agreement release test, Projected DSCR may use only cash arising under the three Qualified SPAs identified below. Non-reserve account interest, insurance, merchant or spot sales, owner support, and other cash sources are excluded. Gas and transportation pass-through receipts and the matching gas and transportation cash costs are both excluded. Historical DSCR uses the Common Terms Agreement Cash Flow definition.

If the conditions are satisfied, any amount then standing to the credit of the Distribution Account may be released; DSCR headroom does not itself create or cap cash. Amounts retained in the Distribution Account may be transferred back to the Revenue, Operating, or Debt Payment Account for project costs or senior debt service without satisfying the Restricted Payment test.

If the release conditions are not met on four consecutive Quarterly Payment Dates, PML must instruct the trustee within three business days to apply the trapped balance to mandatory prepayment. A quarter before Project Completion does not enter the count.

For each Payment Date through 31 January 2020, Schedule 6 fixes the aggregate Required DSRA Amount at $360.0 million. An Eligible Reserve LC must be irrevocable, drawable by the trustee, issued by a bank rated at least A-/A3, and expire no earlier than 30 calendar days after 31 July 2019. If it is not replaced, PML must cash-fund its stated amount five business days before expiry.

Account and funding statement

Balances are as of close of business on 31 January 2019, after that day’s debt service and account transfers:

Controlled account or facilityCash / stated amountStatus and use
Revenue Account96.0Available for project uses; not directly distributable
Operating Account72.0Available for project O&M
Debt Payment Account0.0Next monthly funding transfer occurs after the cut-off
Distribution Account335.0No lien or pending instruction other than the requested payment
DSRA cash160.0Restricted reserve cash
DSRA letter of credit200.0Issued by Granite Coast Bank plc, rated A/A2; irrevocable and drawable; expires 31 August 2019
Additional Proceeds Account25.0Performance-liquidated-damages cash; not transferable to the Distribution Account
Construction Account40.0Restricted to close-out construction claims
Working Capital Facility95.0 commitment; 45.0 drawn50.0 remains committed and available for gas, transport, O&M, or other project working capital; proceeds cannot fund a Restricted Payment

The $200.0 million reserve LC satisfies the contractual eligibility test on 22 February 2019. Granite Coast Bank’s 13 February email quotes a possible $200.0 million replacement LC expiring 31 August 2020 at an upfront fee of 180 bps, subject to fresh credit approval; it is not a commitment and the current LC has no automatic-extension provision. If approved, the fee is payable when the replacement LC is issued. Model v7 predates the quote and includes no renewal fee. Under the financing documents, that fee is an LC Cost outside CFADS and Debt Service but is a project cash use. If no replacement LC is executed, the required $200.0 million cash substitution date is 26 August 2019.

For the lender liquidity tests, Available Project Cash means cash in the Revenue, Operating, and Distribution Accounts. Exclude the Debt Payment Account, DSRA, Additional Proceeds Account, Construction Account, and undrawn Working Capital Facility. The opening amount for the February 2019 forecast is therefore the sum of the three included account balances above. Treat any 22 February distribution as occurring at the start of February for the monthly minimum-cash calculation.

Historical controlled-account ledger

The ledger is final and reconciled to trustee bank statements. Operating receipts include all SPA and merchant operating cash deposited in the Revenue Account. The performance liquidated damages were deposited only in the Additional Proceeds Account. The owner cure cash was deposited in the Revenue Account. Debt Service below already applies the contractual exclusions.

MonthOperating receiptsBI proceedsAccount interestPerformance LDCash O&MSecured-party feesWC interestOwner cure cashDebt Service
Feb-18145.00.00.50.066.01.00.50.00.0
Mar-18146.00.00.50.065.01.00.50.00.0
Apr-18150.00.00.50.067.01.00.50.0170.0
May-18152.00.00.525.068.01.00.513.20.0
Jun-18154.00.00.50.069.01.00.50.00.0
Jul-18158.00.00.50.072.01.00.50.0180.0
Aug-18160.032.00.50.0105.01.00.50.00.0
Sep-18164.00.00.50.069.01.00.50.00.0
Oct-18165.00.00.50.070.01.00.50.0190.0
Nov-18155.00.00.50.084.01.00.50.00.0
Dec-18145.00.00.50.079.01.00.50.00.0
Jan-19130.00.00.50.070.01.00.50.0180.0
Total1,824.032.06.025.0884.012.06.013.2720.0

Borrower’s draft certificate and management model v7

PML’s unsigned 12 February draft certificate reports:

  • Historical CFADS of $998.2 million and Historical DSCR of 1.386x;
  • projected CFADS of $1,045.0 million, Debt Service of $730.0 million, and Projected DSCR of 1.432x;
  • a minimum Available Project Cash balance of $260.0 million after the requested $300.0 million distribution; and
  • all release conditions satisfied.

The model treats the $25.0 million performance liquidated damages and $13.2 million May 2018 owner cure as historical Cash Flow. Its projected numerator includes the Qualified SPA receipts, spot-cargo margin, insurance receipt, and account interest shown below, less non-pass-through O&M, secured-party fees, and Working Capital Facility interest. It excludes the pass-through receipts and costs, turnaround capital expenditure, and Debt Service from that numerator; Debt Service is the denominator. The minimum-cash output assumes the reserve LC renews, uses the forecast cash items exactly as shown, and deducts the proposed distribution at the start of February.

Management forecast v7 — receipts

MonthFixed SPA feesFirm variable SPA marginGas/transport reimbursementSpot marginBI claim receiptAccount interest
Feb-19137.06.048.00.00.00.5
Mar-19137.07.050.00.00.00.5
Apr-19137.07.052.00.00.00.5
May-19137.08.050.014.00.00.5
Jun-19137.08.048.014.00.00.5
Jul-19137.08.046.014.00.00.5
Aug-19137.08.044.00.035.00.5
Sep-19137.08.046.00.00.00.5
Oct-19137.08.050.00.00.00.5
Nov-19137.08.054.00.00.00.5
Dec-19137.08.056.00.00.00.5
Jan-20137.07.052.00.00.00.5
Total1,644.091.0596.042.035.06.0

Management forecast v7 — cash uses

MonthNon-pass-through O&MGas/transport paidSecured-party feesWC interestTurnaround capitalDebt Service
Feb-1958.060.01.00.50.00.0
Mar-1958.055.01.00.50.00.0
Apr-1960.050.01.00.50.0180.0
May-1960.048.01.00.520.00.0
Jun-1962.047.01.00.535.00.0
Jul-1968.045.01.00.50.0180.0
Aug-1968.043.01.00.50.00.0
Sep-1966.045.01.00.50.00.0
Oct-1965.048.01.00.50.0185.0
Nov-1965.052.01.00.50.00.0
Dec-1963.054.01.00.50.00.0
Jan-2062.050.01.00.50.0185.0
Total755.0597.012.06.055.0730.0

The $0.5 million monthly Working Capital Facility cost reflects the existing $45.0 million draw. Additional drawings bear cash interest at 6.5% per year, calculated on actual days and paid monthly; repayments are permitted at any time. For the combined-downside liquidity calculation, assume a new draw occurs on the last calendar day of a shortfall month in the amount needed to restore month-end cash to zero and is repaid on the last day of the first later month with sufficient pre-repayment cash.

Commercial, operating, and funding records received by the cut-off

Qualified SPA terms

The three SPAs were executed before the Calculation Date, remain effective, have investment-grade parent guarantees, and were not in payment default at the cut-off. Their aggregate monthly fixed fee is the $137.0 million shown in model v7. Confirmed cargo nominations support the monthly firm variable margin shown in v7. Fixed fees remain payable when a buyer elects not to lift a cargo, but are reduced for seller unavailability beyond the applicable annual maintenance allowance. Cash is received 20 calendar days after the service month.

Executed price amendment

An amendment to the Bluehaven Power SPA was executed on 10 January 2019. It adds $4.0 million to the monthly fixed fee for service months September through December 2019. Because of the 20-day payment lag, the related cash receipts fall in October 2019 through January 2020. Model v7 does not reflect the amendment.

Independent Engineer outage report

The Independent Engineer’s final report dated 14 February 2019 requires a Train 2 turnaround from 10 May through 23 June 2019. The applicable SPA permits 15 calendar days of seller maintenance without fee reduction; each later outage day reduces the fixed fee by $1.2 million. The first 15 outage days run from 10 through 24 May. Fee reductions follow the SPA’s 20-day payment lag. Model v7 assumes an in-allowance September outage and no fixed-fee reduction. The 15 February nomination and treasury update confirms that the firm variable-margin and gas/transport cash rows in v7 remain unchanged because affected cargoes were rescheduled and those margins are earned on the other trains.

Operator change order and overhaul purchase order

The operator signed a binding change order on 15 February 2019 adding $9.0 million of cash O&M in May and $9.0 million in June. A separate executed overhaul purchase order requires capital payments of $40.0 million in May and $56.0 million in June. Under the financing documents, those overhaul payments are Development Expenditures, not O&M, and therefore are outside contractual CFADS but remain project cash uses. Model v7 includes only $20.0 million and $35.0 million of turnaround capital in those months.

Spot-cargo indications

The $14.0 million margins in May, June, and July are based on nonbinding broker indications dated 11 February. No cargo confirmation, buyer commitment, shipping slot, or hedge had been executed by the cut-off.

Business-interruption claim

The $35.0 million August receipt is PML’s claim amount. The insurer’s 8 February letter acknowledges receipt of the claim but neither admits coverage nor agrees an amount or payment date. The adjuster’s earliest stated decision date is 31 August 2019.

Buyer payment-timing request

Seorim Energy Corporation asked on 12 February to move its scheduled $45.0 million April receipt and $45.0 million May receipt to 30 November 2019. PML rejected the request in writing on 15 February. No amendment or waiver was signed, Seorim and its guarantor remain current, and the original payment dates remain enforceable. Halcyon’s required combined downside below applies the requested deferral without assuming a payment default or acceleration.

Sponsor support letter

Port Meridian Holdings stated on 11 February that it presently intends to contribute up to $150.0 million if needed for the turnaround or DSRA funding. The letter is expressly nonbinding, may be withdrawn without lender consent, and has no funded escrow or guarantee.

Halcyon credit mandate and decision alternatives

For this decision, Halcyon’s approved liquidity tests are:

  • In a committed-resource lender base case, Available Project Cash must not fall below $75.0 million in any month before giving credit to undrawn Working Capital Facility capacity.
  • In the combined downside, the remaining committed $50.0 million Working Capital Facility may be drawn for permitted project uses, but cash after such draws may not be negative at any time. Do not give credit to unsigned cargoes, an unadmitted insurance claim, nonbinding sponsor support, or an uncommitted reserve-LC renewal.
  • Any DSRA cash substitution is excluded from Available Project Cash after transfer. All reserve requirements must remain satisfied.

Build the committed-resource lender base from the operative contracts and records above. Then apply this combined downside to that corrected base:

  1. shift the two Seorim receipts from April and May to November 2019;
  2. reduce each month’s firm variable SPA margin by 25%;
  3. add a 30-day Train 1 outage in September, causing a $30.0 million fixed-fee cash reduction in October and capital repair payments of $10.0 million in September and $10.0 million in October;
  4. increase corrected non-pass-through O&M by 5% in every month; and
  5. assume the reserve LC is not renewed and is replaced with cash when required.

All forecast rows not changed by these five shocks remain at the corrected committed-resource base values.

Halcyon may reject or require correction of a calculation that is not reasonably acceptable or fails an express condition. If every contractual condition is met, Halcyon has no unilateral right to impose the bank’s $75.0 million cash floor or downside test as an additional covenant. A compulsory waiver, amendment, or distribution cap requires holders of 66⅔% of secured debt; Halcyon holds 22% and no vote has been solicited. The sponsor has said it will consider a voluntary staged release if Halcyon distinguishes that request from the trustee’s contractual determination.

If a later tranche is proposed, it can be paid only in a subsequent 25-business-day window after a fiscal-quarter end and only after refreshed 1.25x tests, reserve funding, no-default confirmation, and a new certificate. The next such window follows 30 April 2019.

For sponsor timing comparisons, use a 12.0% effective annual sponsor discount rate and actual/365 timing. Cash retained solely because of staging earns the project 2.25% per year; use that rate only for the incremental timing comparison and leave the $0.5 million monthly account-interest line unchanged in the liquidity schedules. Ignore tax, FX, and transaction costs. No distribution clawback is available.

Harbor submission

Your working directory is /app; resolve the original task's relative paths from there. The supplied inputs are already present in this directory and the paths stated above. Save your complete final answer as UTF-8 text in /app/output/answer.md.